PRC's Major Technology Introducing Projects
(From Year 1993 - 2000)
| 16 | Longtan Hydropower Station in Guangxi Zhuang Autonomous Region | Installed capacity to be 7x6OO,OOO kw |
| 17 | Yangzhou Power Plant in Jiangsu | Installed capacity to be 2x6OO,OOO kw |
| 18 | Beilunggang Power Plant and Transmission Network Renovation in Zhejiang | Installed capacity to be 2x6OO,OOO kw for Phase 11; Project includes renovation of major transmission network |
| 19 | Tuoketuo Power Plant in Inner Mongolia Autonomous Region | Installed capacity to be 2x6OO,OOO kw |
| 20 | Dalian Power Plant, Phase 11 | Plant capacity to be 2x350,000 kw |
| 21 | Qinshan Nuclear Power Plant, Phase 11 | Essential equipment for 2x6OO,OOO kw generating units |
Environmental Protection
| 1 | Comprehensive Environmental Protection Coverage in Hebei | Solve polution problems caused by waste water, slag and gas via new technologies in Chengde and Tangshan Cities |
| 2 | Dalian Water Supply Project | Develop facilities to increase water supply in Biiuhe River to 1.2 million tons per day |
| 3 | Port Environmental Protection | Upgrade port environment protection facilities with the aid of Global Environment Protection Fund |
Forestry/Paper
| 1 | Particle Board Project at Wuchagou Forest Bureau of Xing-An Prefecture, Inner Mongolia Autonomous Region | Develop facilities to process 405,000 cubic feet of particle board per year |
Copyright (c)1999 theshipping.com All rights reserved.